End Customer: Clarenceville School District
Location: Livonia, MI
Date: August 2026


Project Overview

In late 2025, Clarenceville School District contacted Farnham Equipment Company (FEC) to assist with a seat replacement project for their main gymnasium. The existing seats on the home side bleachers were worn and in need of replacement, with the understructure working capably. Upon getting in contact with FEC, the school issued a notice to proceed on the replacement seat project for the summer of 2026. The scope included:

  • Removal and disposal of the seats on tiers 1-7 of the home bleachers
  • Installation of new Courtside 10” seats 
  • Utilize the MVP seats from the home side to replace damaged seats on the visitor side bleachers

This project came together quickly, as the customer opted to use Sourcewell to purchase directly from FEC, while looking to complete the work prior to students returning for the 2026 school year. FEC’s installation team was lauded for its professionalism and expertise from start to finish on this project.


Key Project Features

1. Telescoping Bleachers: Hussey Seating Company

The new seating replacement at Clarenceville High School included:

  • (40) 10” starter seats, Color #050 Grey
  • (312) 10” intermediate seats, Color #050 Grey
  • (136) 10” intermediate seats, Color #187 Red
  • Purchased through Sourcewell
https://www.flickr.com/photos/farnham-equipment-company/albums/72177720335525010